dc.contributor.advisorUlloa Velásquez, Félix Wilfredo-
dc.contributor.authorZarzo Aquise, José Luis-
dc.creatorZarzo Aquise, José Luis-
dc.date.accessioned2020-02-27T15:48:41Z-
dc.date.available2020-02-27T15:48:41Z-
dc.date.issued2019-
dc.identifier.urihttp://hdl.handle.net/20.500.14076/18999-
dc.description.abstractEl seguimiento y control de proyectos son procesos que consisten en revisar y comparar los avances con los desempeños proyectados y tomar acciones con la finalidad de concluir el proyecto dentro de lo establecido. Sin embargo, la realización de estos procesos genera exceso de consumo de tiempo, imprecisiones y falta de facilidad de entendimiento en la elaboración de reportes de avance debido a la falta de automatización, integración y síntesis de los sistemas de seguimiento y control tradicionales. Este trabajo de investigación propone la implementación de un sistema seguimiento y control de tiempo y costo en las obras civiles de un proyecto petroquímico, con la finalidad de evaluar sus impactos sobre los procesos de seguimiento y control de proyectos. El sistema BIM se implementó específicamente en la ejecución de las obras civiles del centro de costo Pipe Rack de Prefabricados del proyecto petroquímico Gasolinas en dos fases, que en su conjunto consistió en una evaluación previa de sus sub proyectos para determinar la factibilidad de implementación de las etapas del sistema; luego se procedió a desarrollar las etapas, que en síntesis son la modelación 3D, la conexión y automatización del flujo de información y finalmente la visualización de los avances. La propuesta de implementación BIM es un sistema que almacena la información obtenida de los avances diarios de obra en parámetros de costo y tiempo creados de acuerdo a las estructuras de los formatos de valorización y cronograma, para luego ser procesados por el programa de modelación Revit de Autodesk. Este procesamiento consiste, en primer lugar, en la organización de data que luego se exporta a los formatos de valorización y cronograma, mediante cuadros de conexión; y segundo, la actualización de vistas de avance mediante el funcionamiento de parámetros condicionales y fórmulas de cálculo y sintetización de información. Por otro lado, este sistema también está apoyado en cuadros de cálculo y programas de gestión de proyectos, que procesan la data exportada del modelo ejecutando cálculos propios de valorización y planificación respectivamente. La documentación de sustento de los informes de avance se logra obtener a partir de estos dos procesos principales. La implementación del sistema propuesto permitió realizar el proceso de seguimiento y control de manera diaria y oportuna respectivamente; facilitando la obtención de las mediciones, costos y porcentajes de avance con precisión, como también conectando la valorización y cronograma con una única fuente de información; evitando el conteo doble y omisiones, debido a la gran cantidad de variables, en el cálculo de los metrados, evitando así la pérdida de tiempo por correcciones; dando un entendimiento visual del estado actual del proyecto, gracias a las vistas 3D, disminuyendo así la necesidad de los gerentes de construcción de hacer visitas a obra; y finalmente, permitiendo tratar gran cantidad de información detallada, más que nada gracias al modelo 3D por la utilización de parámetros y filtros.es
dc.description.abstractThe monitoring and control of projects are processes that consist in the review and comparison of the progress with the projected performances and actions with the purpose of concluding the project within the established. However, the realization of these processes generates a consumption of time, inaccuracies and lack of easy understanding in the preparation of progress reports due to the lack of automation, integration and synthesis of traditional monitoring and control systems. This research work proposes the implementation of a monitoring system and the control of time and cost in the civil works of a petrochemical project, with the purpose of evaluating the effects of the monitoring and control processes of projects. The BIM system was implemented especifectly in the execution of the civil works of the cost center Prefabricated Pipe Rack of the Gasolinas petrochemical project in two phases, which as a whole consisted in a prior evaluation of its sub-projects to determine the feasibility of the implementation of the system stages; then proceeded to develop the stages, which in the synthesis are 3D modeling, the connection and automation of the flow of information and finally the visualization of progress. The BIM implementation proposal is a system that stores the information obtained from the daily progress of work in cost and time parameters created according to the structures of the budget and schedule formats, to be later processed by the Revit modeling program. of Autodesk. This processing consists, first of all, in calculations and the organization of data that is then exported to the budget and schedule formats, through connection tables; and second, the update of advance views through the operation of conditional parameters and formulas for calculation and synthesis of information. On the other hand, this system is also supported by calculation tables and project management programs, which process the data exported from the model by executing calculations of budget and planning respectively. The documentation of the support of the progress reports is obtained from these two main processes. The implementation of the proposed system allowed to carry out the monitoring and control process in a daily and timely manner, respectively; facilitating the obtaining of the measurements, costs and percentages of advance with precision, as well as connecting the budget and chronogram with a single source of information; avoiding double counting and omissions, due to the large number of variables, in the calculation of the measurements, thus avoiding the loss of time by corrections; giving a visual understanding of the current status of the project, thanks to the 3D views, thus decreasing the need for construction managers to make site visits; and finally, allowing us to deal with a large amount of detailed information, mainly thanks to the 3D model due to the use of parameters and filters.en
dc.description.uriTesises
dc.formatapplication/pdfes
dc.language.isospaes
dc.publisherUniversidad Nacional de Ingenieríaes
dc.rightsinfo:eu-repo/semantics/openAccesses
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/4.0/es
dc.sourceUniversidad Nacional de Ingenieríaes
dc.sourceRepositorio Institucional - UNIes
dc.subjectBuilding Information Modeling (BIM)es
dc.subjectObras civileses
dc.subjectProyectoses
dc.titleImplementación de un sistema de seguimiento y control usando BIM en las obras civiles de un proyecto petroquímicoes
dc.typeinfo:eu-repo/semantics/bachelorThesises
thesis.degree.nameIngeniero Civiles
thesis.degree.grantorUniversidad Nacional de Ingeniería. Facultad de Ingeniería Civiles
thesis.degree.levelTítulo Profesionales
thesis.degree.disciplineIngeniería Civiles
thesis.degree.programIngenieríaes
renati.advisor.orcidhttps://orcid.org/0000-0002-8773-9590es
renati.author.dni70494726-
renati.advisor.dni07227448-
renati.typehttp://purl.org/pe-repo/renati/type#tesises
renati.levelhttp://purl.org/pe-repo/renati/nivel#tituloProfesionales
renati.discipline732016-
renati.jurorGotelli Villanueva, Luis Ivan-
renati.jurorRíos Segura, Juan Guillermo-
dc.publisher.countryPEes
dc.subject.ocdehttp://purl.org/pe-repo/ocde/ford#2.01.01es
Aparece en las colecciones: Ingeniería Civil

Ficheros en este ítem:
Fichero Descripción Tamaño Formato  
zarzo_aj.pdf11,01 MBAdobe PDFVisualizar/Abrir


Este ítem está sujeto a una licencia Creative Commons Licencia Creative Commons Creative Commons

Indexado por:
Indexado por Scholar Google LaReferencia Concytec BASE renati ROAR ALICIA RepoLatin UNI